Home

Featured Bridge

Contact

Bio

Books, BridgeStories,
& Other Curriculum

Bridge Walks
Other Events

Virtual Tour
Morrison Bridge

Bridge Bios

Poetry

Links

Other

 
 

Featured Span: Sauvie Island Bridge

Sauvie Island Float-In and
Bridge Lift

See also: photo essay.

On December 28, 2007 the Sauvie Island Bridge’s arch span was barged eight miles from Terminal 2 along Front Avenue down the main channel and Multnomah Channel of the Willamette River. Four tugs pushed it into place between new concrete piers located south of the old 1950 bridge and the only entrance and exit to and from Sauvie Island. This is the first new big river bridge built by Multnomah County in fifty years.* Funding for the new bridge was secured mainly through the efforts of Multnomah County Commissioner Maria Rojo de Steffey.

These are my photos documenting the arch’s journey.

The arch, 365 feet long, 77 feet tall, 1,600 tons, and held together by 80,000 high-strength bolts, needed to be jacked up high enough to be set down on the pier tops 70 feet above zero water. The flags you see in the photo above are waving 185 feet above the Willamette River.

The float-in was delayed several times. Ed Wortman, engineering advisor for Multnomah County for the construction, float-in, and lift of the Sauvie Island Bridge, was scheduled to retire from the County the end of November 2007, but stayed an extra month to help with the lift and float-in—delayed due to weather, getting the right barge (the one used, arriving here from Alaska, was 84 wide and 300 feet long), and other unforeseen events.

There were additional delays in December and we wondered if Ed was going to be around—his last day of paid work for Multnomah County was to be December 28, 2007. The four Foss tugboats turned the arch and moved it in place at about 11 a.m. that same day, a perfect ending for this engineer who’s been sliding his rule for 47 years now at some very exciting elevations. Ed came to Portland in 1971 and helped with the construction of the Fremont Bridge, also an arch like the new Sauvie Island Bridge — the latter job bringing Ed’s career in Portland full circle.

Scott Bronson, the Webmaster for <www.bridgestories.com>, recently asked why the bridge wasn’t jacked up to its final height at the new site rather than at Terminal 2, and was there ever a worry about the arch tipping because of the high center of gravity?

Ed Wortman responds:

Jacking the span up at the Terminal 2 dock was much easier than jacking it at the site. Skidding the arch out onto the barge was the hardest part of the job. The crew was out there from 11 a.m. Saturday until 12:30 p.m. on Sunday—24 hours in the worst, wet, most awful weather.

After the arch was in the air, the back end of the skid units on land—pushed with jacks. The front end, on the barge, was on rollers. This proved to be way more complicated that floating the bridge up the river.

In each of the four jacking towers is a stack of hardwood, 4”x4” and 48" long. The span was jacked up eight inches at a time. The contractor used a clever system where they put the pieces of wood in two layers at a time at the bottom of the stack, then jacked those layers, gradually lifting the arch up.

NORSAR, an engineering transport and lifting company that specializes in moving barges and other large industrial objects, developed this jacking system in Chicago to lower a 700-ton German submarine into an underground gallery in the Chicago Museum of Science and Industry in 2005.

The Sauvie Island Bridge could have been even heavier, and it wouldn’t have been a problem.

*Multnomah County owns and maintains the Sauvie Island, Hawthorne, Morrison, Burnside, Broadway, and Sellwood bridges across the Willamette River and more than 20 smaller bridges in East Multnomah County

>> Featured Bridge Archive <<

 

 
 
www.bridgestories.com